摘要
介绍了采用三台阶七步开挖法进行隧道施工的技术特点,以某隧道施工为例说明了洞体开挖中的各工序要点,重点在于初期支护尽快闭合成环,及时跟进仰拱和拱墙衬砌,强调了确保施工质量的控制要点,以确保洞体施工质量和安全。
This paper introduced the technical characteristics using three steps seven footwork excavation method to tunnel construction,taking a tunnel construction as an example,explained the key points of each process,center on the initial support closed as soon as possible,and the inverted arch and arch wall lining followed up in time,emphasized the key points of ensuring the construction quality,so as to ensure the tunnel construction quality and safety.
作者
聂永岗
Nie Yonggang(Shanxi Jinzhong Road and Bridge Construction Group Limited Company,Jinzhong 030600,Chin)
出处
《山西建筑》
2018年第18期150-151,共2页
Shanxi Architecture
关键词
台阶法
隧道
支护
step method
tunnel
support