综采工作面过断层顶板控制措施研究 被引量:11

Study on Roof Control Measures in Fully Mechanized Mining Face Passing Through the Fault
下载PDF
导出
摘要 综采工作面过断层带期间受构造应力影响,断层上下盘附近煤岩体出现破碎现象,若不及时采取合理的顶板控制措施,不仅影响着工作面正常移架,降低了工作面回采效率,而且很容易发生重大煤矿安全事故。本文以西曲矿28302工作面为例,提出了合理有效的工作面过断层顶板控制措施,确保综采工作面安全顺利回采。 When the fully mechanized coal face passes through the fault zone, affected by the tectonic stress, coal and rock mass over & under the plate will be broken. if rational roof control measures are not taken, not only affects the normal movement of the working face, reduces the mining effciency of the working face, but it's also easy to lead to major coal mine safety accidents. Taking the working face of 28302 in Xiqu Mine as an example, this paper puts forward reasonable and effective roof control measures of working face passing over fault to ensure the safe and smooth recovery of fully mechanized mining face.
作者 郭太斌 Guo Tai-bin(Gujiao Xiqu Mine,Xishan Coal and Electricity,Shanxi Coking Coal Group,Shanxi Gujiao 03020)
出处 《山东煤炭科技》 2018年第7期16-17,共2页 Shandong Coal Science and Technology
关键词 综采 断层 措施 fully mechanized mining fault measures
  • 相关文献

参考文献5

二级参考文献24

共引文献42

同被引文献38

二级引证文献25

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部