摘要
本文根据高速公路风化石土包砂路基填筑压实实验及施工实践,介绍了施工中应注意的施工要点及其薄弱环节应对办法和质量控制方法。
Base on compaction experiment and construction practice of the expressway constructed by filling subgrade with wrap sand in landwaste,introduce key construction points,corresponding solution for weakness tache,and method for quality control and check.
出处
《科技传播》
2011年第12期53-54,52,共3页
Public Communication of Science & Technology
关键词
风化石土包砂
路基
施工技术
压实度
质量控制与检测
Wrap sand with landwaste
Subgrade
Construction techniques
Compaction degree
Quality control and check