摘要
在分析山西左权盘城岭煤业采煤工作面的基础上,采用放顶煤综采工作面三机配合方案,使采煤机、前后刮板输送机、液压支架在结构参数、使用性能等方面进行匹配,探讨出一种合理高效的采煤流程,对类似煤矿企业的"三机"选型具有现实的参考价值。
On the analysis of coal mining face of Panchengling Mine,Zuoquan,Shanxi Province,a three-machine plan for the fully-mechanized top-coal caving face is designed to match the structural parameters with the performance of shearers,front and rear scraper conveyors,and hydraulic supports.Then,the paper proposes a reasonable and efficient coal mining process,which could be as a reference for the three-machine selection of the similar coal mine enterprises.
作者
史红瑞
SHI Hongrui(Shanxi Coal Construction Project Management Co.,Ltd.,Taiyuan 030012,China)
出处
《山西煤炭》
2018年第3期66-68,共3页
Shanxi Coal