摘要 基于对陕西正通煤业有限责任公司巷道条件和煤层钻孔施工特点分析,对现有冲击地压超前卸压钻孔施工工艺及施工效果进行分析,并针对问题提出解决方案。通过对钻具组合及施工工艺的优化,经过现场试验,最终形成一套适合正通煤业冲击地压超前卸压钻孔高效成孔施工的最优设备、钻进工艺方法及工艺参数,达到冲击地压防治目标的同时,实现安全生产、降本增效,为该公司实现"掘卸平行"的高效生产提供保障。 The conditions of coal mine roadway and the construction characteristics of coal seam drilling in Shaanxi Zhengtong Coal Industry Company were analyzed,and the construction technology and construction effect of the existing impacting pressure and pressure relief drilling were analyzed,solutions to the problem were also put forward. According to the optimization of the drilling tool combination and the construction technology,through the field test,a set of optimal equipment,drilling technology and process parameters suitable for the high effect hole construction of the pre pressure relief drilling were finally formed for Zhengtong Coal Industry Company,so as to achieve the safety production,reduce the cost and increase the efficiency at the same time. It also has provided guarantee for the realization of " parallel operation of driving and pressure relief" in Zhengtong Coal Industry Company.
作者 王博 魏宏超 Wang Bo;Wei Hongchao(Xi'an Research Institute of China Coal Technology & Engineering Group Corp,Xi'an 710077,China)
出处 《能源与环保》 2018年第6期44-47,共4页 CHINA ENERGY AND ENVIRONMENTAL PROTECTION
关键词 冲击地压 超前卸压 掘卸平行 ZDY4000LR rockburst advanced pressure relief parallel operation of driving and pressure relief ZDY4000LR
  • 相关文献

参考文献11

二级参考文献74

共引文献1240

同被引文献6

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部