摘要 上海市轨道交通L18一期工程两港φ3 000 mm合流截流污水总管改迁后需近距离下穿现有高危居民住宅,通过总结盾构施工过程中建筑物的沉降规律,严格控制盾构穿越施工参数,并在施工过程中采取Clay-shock工法减少构筑物沉降,相关经验可为类似工程的施工提供参考。 With the background of Shanghai Rail Transit L18 Project(Phase I), the confluent &intercepting sewage pipe of two harbors withφ3 000 mm should underneath pass the existing high-risk residential buildings. By summing up the laws of building settlement during the shield construction,the construction parameters are strictly controlled and the Clay-Shock method is adopted to reduce the structure settlement during the construction process. The related experience can provide reference for similar projects.
作者 戴晟磊
出处 《中国市政工程》 2018年第3期100-102,共3页 China Municipal Engineering
关键词 盾构隧道 浅基础 沉降控制 施工技术 shield tunnel shallow foundation settlement control construction technology
  • 相关文献

参考文献2

二级参考文献9

共引文献42

同被引文献12

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部