基于改进粒子群算法的高效船体分段制造优化 被引量:1

Optimization of Efficient Hull Block Manufacturing Based on Improved Particle Swarm Optimization
下载PDF
导出
摘要 针对船体分段制造计划通常受到分段装焊场地、作业设备和作业工序等因素限制,以按需拉动、负荷平衡、缩短周期为优化目标,构建了高效分段制造作业计划优化模型。考虑作业优化模型变量离散和非线性问题,采用改进的粒子群算法,对优化模型进行求解。通过对某船厂实例分析,经Matlab编程运行,表明优化算法对提高分段制造产能、缩短建造周期具有较为明显的效果。 An optimization model of efficient ship hull block manufacturing scheduling is presented. The model seeks to drive the production with a pull system, balance the load, and shorten the production cycle. The hull block manufacturing schedule is usually restricted by the assembling and welding sites, operation equipment and working procedure. An improved particle swarm optimization algorithm is used to solve the optimization model with discrete and nonlinear variables. A real-world case study from a shipyard is taken as an example to verify the effectiveness of the model. The implementation is done in MATLAB. The computational experiment result shows that the optimization algorithm is effective in improving the hull production capacity and shortening the construction cycle.
作者 蒋革 冯定忠 朱伟杭 JIANG Ge;FENG Dinzhong;ZHU Weihang(Zhijiang College,Zhejiang University of Technology,Hangzhou 310024,China;School of Mechanical Engineering,Zhejiang University of Technology,Hangzhou 310014,China;Department of Industrial Engineering,Lamar University,Beaumont 77710,Texas,USA)
出处 《工业工程》 北大核心 2018年第3期65-74,共10页 Industrial Engineering Journal
基金 浙江省公益技术应用研究计划资助项目(2014C33112) 浙江省船舶工业转型升级重点资助项目(2014C30)
关键词 船体分段 作业计划 改进粒子群算法 hull block manufacturing schedule particle swarm optimization
  • 相关文献

参考文献2

二级参考文献10

  • 1Lee J K,Lee K J, Park H K, etal. Developing scheduling systems for Daewoo shipbuilding: DAS project [J]. European Journal of Operational Research, 1997, 97(2) :380-395.4.
  • 2Cho K K, Chung K H, Park C, etal. A spatial scheduling system for block painting process in shipbuilding [J].CIRP Annals-Manufacturing Technology, 2001, 50(1) :339-342.
  • 3Park C, Chung K H, Park J C, etal. A spatial scheduling application at the block paint shop in shipbuilding: the HYPOS project [J]. Production Planning & Control, 2002,13(4) :4342-4354.
  • 4Varghes R J, Yoon D Y. Dynamic spatial block arrangement scheduling in shipbuilding industry using genetic algorithm [C]// 3rd IEEE International Conference on Industrial Informatics. India: [s. n.], 2005:444-449.
  • 5Li B, Zhan Z Y, Li G. A dynamic scheduling method for spatial layout planning [C]//Proceedings of the Fourth International Conference on Machine Learning and Cybernetics. Guangzhou: [s. n. ] ,2005 : 18-21.
  • 6Eom C H, Jang J H, Koh S G. Block assembly scheduling in shipbuilding company EC3//Proceedings of the 37th International Conference on Computers and Industrial Engineering. Egypt:[ s. n. ], 2007,10 : 20-23.
  • 7Park K,Computers Ind Eng,1996年,30卷,357页
  • 8Lee T E,J Ship Production,1996年,12卷,4期
  • 9屈婉玲,组合数学,1989年
  • 10张志英,王蕾,江志斌,李珍.面向船体曲面分段建造的空间调度方法[J].上海交通大学学报,2008,42(4):569-573. 被引量:20

共引文献27

同被引文献7

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部