摘要
文章以某城市地铁盾构隧道与既有建筑物桩基相冲突的工程实例,阐述了特殊条件下,不做桩基托换,采用盾构机直接截桩穿越建筑物桩基的关键技术措施,最终在确保建筑物安全的同时,成功地解决了制约整条地铁线路通车的关键难题。
This paper illustrates the key of a metro shield tunnel in a city that conflicts with a building foundation. The key to using a shield machine to directly cross a building pile foundation without a pile foundation under special conditions is described. Technical measures, while ensuring the safety of buildings, have successfully solved the key problems that constrain the opening of the entire subway line.
出处
《科技创新与应用》
2018年第21期130-131,共2页
Technology Innovation and Application
关键词
盾构
截桩穿越
建筑物桩基
shield
pile-cutting crossing
building pile foundation