装配整体式混凝土结构改变了现浇建筑的建造方式,使得设计、施工、建设过程的各个环节发生了重大变化。结合装配整体式工程的特点,在对预制构件生产、吊装、连接、灌浆等环节分析的基础上,从监督制度建设、现场安全质量监督等方面提出相对应的措施。
The assembly of monolithic concrete structure has changed the construction mode of cast-in-place buildings,making significant changes in all aspects of design,construction and construction process. Based on the characteristics of assembly integrated engineering,based on the analysis of precast component production,hoisting,connection and grouting,the corresponding measures are put forward from the aspects of supervision system construction,on-site safety and quality supervision.
作者
瞿志勇
QU Zhiyong(Pudong New Area Construction Engineering Safety and Quality Supervision Station Shanghai 200127 China)
出处
《工程质量》
2018年第6期5-9,共5页
Construction Quality
关键词
装配整体式
实践
吊装
方案
监督措施
assembled monolithic concrete structure
practice
hoisting
scheme
supervision measures