摘要 核电站DCS系统作为集中控制平台,面临着和多个第三方系统通信,但双方并非进行了高精度的时间同步,现场信号到达DCS的传输时间不得而知。本文巧妙的设计一种方式,通过注入和输出的波形比较,测算出两者之间数据的传输时间,为通信方式的选择及通信参数优化设置提供了依据。 Nuclear power plant DCS system as the centralized control platform is faced to multiple third-party systems for communication. But both sides do not take high-precision time synchronization so that the transmission time of field signal to DCS is unknown. This paper has ingeniously designed a method by comparing the injection and export waveforms to measure the data transmission time between both and provide basis for the selection of communication method and communication parameter setting.
作者 王东晓 郑文斌 谈代林 Wang Dongxiao;Zheng Wenbin;Tan Dailin(Guangxi FangChengGang Nuclear Power Co.,Ltd.,Guangxi,Fangchenggang,538000,China)
出处 《仪器仪表用户》 2018年第7期80-84,共5页 Instrumentation
关键词 核电站 信号通信时间 测量 火警探测系统 nuclear power plant signal communication time measurement fire detection system
  • 相关文献

参考文献3

二级参考文献6

共引文献3

同被引文献5

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部