贝雷支架法在连续刚构桥边跨现浇段施工中的应用 被引量:2

Application of Bailey Stent Method in Construction of Side-span Cast-in-situ Section of Continuous Rigid Frame Bridge
下载PDF
导出
摘要 文章结合都安至武鸣公路工程红渡红水河大桥施工实例,介绍了连续刚构桥边跨现浇段贝雷支架法设计与施工技术,并通过贝雷支架受力验算,验证了该桥贝雷支架法施工的合理性。 Combining the construction practices of Hongdu Hongshui River Bridge in Duan-Wuming Highway project,this article introduced the design and construction technology of Bailey stent method for side-span cast-in-situ section of continuous rigid frame bridge,and verified the construction rationality of this bridge by Bailey stent method through the force checking of Barley stent.
作者 李世艺 LI Shi-yi(Guangxi Road Construction Engineering Group Co., Ltd., Nanning, Guangxi, 53000)
出处 《西部交通科技》 2018年第5期109-112,共4页 Western China Communications Science & Technology
关键词 边跨现浇段 贝雷支架 验算 预压 Side-span cast-i n-situ section Bailey stent Checking Pre-compression
  • 相关文献

参考文献2

二级参考文献8

  • 1中华人民共和国建设部.建筑结构荷载规范GB50009-2001.北京,2002(The Ministry of Construction of the People's Republic of China.Standard of Structure Loads of the Building GB50009-2001.Beijing,2002
  • 2公路桥涵施工技术规范JTJ041-2000(人民交通出版社2000.北京).
  • 3周水兴等.路桥施工计算手册[M].北京:人民交通出版社,2003.
  • 4GB50010-2002.混凝土结构设计规范.[S].,..
  • 5钢结构设计规范.GB50017—2003.北京:中国建筑工业出版社,2003.
  • 6叶代成.水上现浇箱梁支架搭设施工技术.
  • 7JTJ 041-2000.公路桥涵施工技术规范[S]..2000
  • 8JTJ 053-1994.公路工程水泥混凝土试验规程[S]..1994

共引文献5

同被引文献9

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部