摘要
介绍濛里枢纽二线船闸工程测量、勘察阶段中适宜BIM设计的勘测手段及成果处理方法,阐述船闸三维建模思路,分析REVIT软件的2种协同模式,提出将船闸工程项目模型划分为若干个子模型、采用工作集与动态链接相结合的协同方式,并给出模型的划分思路及协同方法;探索BIM模型与有限元计算软件间的数据交换方式;结合水运工程BIM标准化发展战略的要求,创建大量标准族并开发了族管理器,初步形成《船闸BIM设计指南》。
This paper introduces appropriate BIM design survey methods for Mengtze junction second line shiplock project in measurement & survey phases and the results processing methods,expounds the idea on the 3D modeling for the shiplock,analyzes the two cooperative modes of software REVIT,and proposes a cooperative model applicable to the ship lock engineering, i. e. dividing the project model into several sub-models and using a collaborative approach which combines working sets and dynamic links to design.This paper also analyzes the data exchange between BIM model and finite element calculation software.According to the requirements of standardized design to improve design quality and efficiency,a family library is created and a family manager is developed,and initially the Ship lock BIM Design Guide is compiled.
作者
刘江林
宋文涛
徐军辉
王平
LIU Jiang-lin;SONG Wen-tao;XU Jun-hui;WANG Ping(CCCC Second Harbor Consultants Co.Ltd.Wuhan 430060 Chin)
出处
《水运工程》
北大核心
2018年第8期135-139,149,共6页
Port & Waterway Engineering
关键词
BIM
船闸
协同
设计
BIM
shiplock
collaboration
design