遭遇破碎带是TBM掘进中的重大风险。掘进受阻处理是施工处理技术难点。本文以兰州市水源地建设工程为例,详细记述了采取"化灌止浆墙+超前灌浆"处理措施,双护盾TBM成功通过破碎带的施工过程,并提出了地质勘察及预报、破碎带处理准备及实施、双护盾TBM设计改进三个方面的建议,可为此类工程提供借鉴。
It is a major risk in TBM tunneling to encounter the rupture belt.How to deal with tunneling blocking is a difficult problem in construction treatment.Water source construction project of Lanzhou is adopted as an example.The construction process of the double shield TBM successfully passing through the fracture zone by using ‘chemical perfusion slurry wall + advanced grouting'treatment measures is accounted in detail in the paper.Suggestions in three aspects of geological investigation and forecast,fracture zone processing preparation and implementation,double-shield TBM design improvement are proposed,thereby providing reference for similar projects.
作者
王耀
张高
WANG Yao;ZHANG Gao(Yellow River Survey and Planning Design Co.,Ltd.,Zhengzhou 450003,China)
出处
《水利建设与管理》
2018年第7期10-13,53,共5页
Water Conservancy Construction and Management
关键词
隧洞
双护盾TBM
破碎带
受阻
处理
经验
tunnel
double-shield TBM
rupture zone
blocking
processing
experience