摘要
马马崖一级水电站进水口、尾水出口板梁由于各种因素的限制,无法采用预制安装的施工方式,本文提出了以贝雷架为支撑,拉筋反拉的板梁整体现浇施工方案。该方案在保证板梁浇筑质量及施工安全的前提下,缩短了施工进度,节约了大型起重吊装设备租赁成本,效果良好。
Mamaya level I hydropower station water inlet and tail water outlet plate girder cannot be constructed in the mode of prefabricated installation due to restriction of various factors.Integral cast-in-place construction plans of plate girder are embodied with Bailey truss as support,which is pulled backwards by tie bars.The plan shortens the construction progress,and saves the lease cost of large hoisting equipment under the precondition of ensuring plate girder casting quality and construction safety,thereby achieving sound effect.
作者
毛应飞
刘朝建
MAO Yingfei;LIU Chaojian(Guizhou Beipanjiang Electric Power Co.,Ltd.,Guiyang 550002,China;China Water Conservancy and Hydropower Ninth Engineering Bureau Co.,Ltd.,Guiyang 550002,China)
出处
《水利建设与管理》
2018年第7期22-25,30,共5页
Water Conservancy Construction and Management
关键词
水电站
贝雷架
大跨度板梁
整体现浇
hydropower station
Bailey truss
long-span plate girder
integral cast-in-place