结合七孔闸工程消力池段工程地质条件,通过方案比选,选定管井井点降水方法为该工程基坑排降水,并介绍其设计计算及施工要点。方案实施后,达到了预期效果,确保了消力池段的顺利完工,其经验可供类似工程借鉴。
For the foundation pit dewatering of stilling basin construction of Qikong Gate Project, pipe well point dewatering was adopted after schemes were compared combining with the engineering geological conditions. An instruction was made on the key points of design and construction. The adopted scheme had been implemented with the desired effects achieved, ensuring successful completion of the stilling basin.
作者
高树天
周明
GAO Shu-tian;ZHOU Ming(Shenyang Water Conservancy Institute,Shenyang110015,China)
出处
《广西水利水电》
2018年第3期61-63,共3页
Guangxi Water Resources & Hydropower Engineering
关键词
管井
井点降水
七孔闸
Pipe well
well point dewatering
Qikong gate