摘要 依托某大桥24个水中承台的施工,结合工程现场地质水文条件和无大型水上起重设备的施工条件,提出了适用于浅水、岩基承台施工的外封堵式预应力组合钢套箱施工技术。该技术充分利用现场地质条件,创造性地实施了套箱外部封堵技术,减少了基坑的开挖量,适用于埋深不大的岩基承台施工。 Based on the construction of 24 offshore cushion caps in a bridge, combined with the geological and hydrographic conditions of the project and the construction conditions of no heavy lifting equipment on water, we proposed an external plugging prestress steel cofferdam construction technology for shallow water and rock base platform. This technology takes full advantage of the site geological conditions, creatively implemented the external plugging of steel cofferdam, decreased the excavation quantity of the foundation pit, and it is suitable for the construction of cushion cap in a shallow burial rock ground condition.
作者 严小卫 吴立柱 YAN Xiao-wei;WU Li-zhu(The 3rd construction Company of CCCC Second Harbor Engineering Co.,Ltd.,Zhenjiang,Jiangsu 212003,China)
出处 《中国港湾建设》 2018年第7期57-60,共4页 China Harbour Engineering
关键词 桥梁工程 承台 预应力 组合式钢套箱 外封堵 bridge construction cushion cap prestress steel cofferdam external plugging
  • 相关文献

参考文献5

二级参考文献10

共引文献31

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部