摘要
结合超高层建筑施工中非标准层与变截面的施工,通过方案优化,采取针对性的措施,解决了因结构变化带来的施工难题。实践证明,针对性的技术措施及施工工序优化,缩短了工期,保证了进度,可为类似工程提供借鉴。
In combination with the construction of non-standard floor and variable cross-section climbing formwork in super high-rise buildings, and through optimization of construction scheme and adoption of targeted measures, relevant construction difficulties caused by structural changes have been solved. Practice has proved that such targeted technical measures and optimization of construction processes shorten the construction period and ensure the construction progress, which can provide references for similar projects.
作者
成禹
CHENG Yu(Shanghai Construction Group Co.,Ltd.,Shanshai 200080,China)
出处
《建筑施工》
2018年第4期557-559,共3页
Building Construction
关键词
超高层建筑
变截面
非标准层施工
液压爬模
super high-rise building
variable cross-section
non-standard floor construction
hydraulic climbing formwork