摘要 既有铁路顶进涵施工时,既有行车未中断,施工单位经验不足,施工安全隐患极大。尤其是在高低温季节,铁路线路极易在钢轨内部温度力的作用下失稳,危及行车安全,因此在铁路线路加固被架空期间,必须改变钢轨受力状况。结合南昆线下穿顶进涵施工经验,阐述了施工安全注意事项,对在施工地段为保持既有线稳定而应设置的两端轨缝大小进行了分析,为下穿既有铁路顶进涵施工提供了依据、经验与借鉴。 During jacking culvert construction of the existing railways, the existing traffic is not stopped, the construction unit is lack of experience, and the potential construction safety hazard is great. Especially in the high and low temperature season, the railway line is easy to lose stability under the action of internal temperature force of steel rails, which endangers traffic safety, therefore during the railway line reinforcement and being placed overhead, the rail stress condition must be changed. In combination with the construction experience of the jacking culvert un- der the Nankun railway line, the relevant construction safety precautions are described, and the setting of rail joints at both ends of the construction section to maintain the stability of the existing line was analyzed, so as to provide the basis, experience and reference for the jacking culvert construction undercrossing the existing railways.
作者 朱德稳 Zhu Dewen(Baise Railway Section,China Railway Nanning Group Co.,Ltd.,Baise 533000,Guangx)
出处 《工程建设》 2018年第7期79-82,共4页 Engineering Construction
关键词 顶进涵 线路稳定 轨缝 jacking culvert line stability rail gap
  • 相关文献

参考文献4

二级参考文献6

  • 1[5]TB 10002.5-2005 铁路桥涵地基和基础设计规范[S].北京:中国铁道出版社,2005.
  • 2广钟岩,高慧安.铁路无缝线路[M].北京:国铁道出版社,2012.
  • 3TB 10303-2009.铁路桥涵工程施工安全技术规程[S],2009.
  • 4TB 10305-2009. 铁路轨道工程施工安全技术规程(S)2009
  • 5TB 10301-2009. 铁路工程基本作业施工安全技术规程(S)2009
  • 6TZ 324-2010. 铁路预应力混凝土连续梁(刚构)悬臂浇筑施工技术指南(S)2010