摘要
分析了建筑工程车库回填土工序对施工项目总工期的影响,对在车库回填土工程本身制约因素、以及冬季施工、种植节点、扬尘治理等环境因素影响下,如何采取合理的管理及技术措施以实现工程项目总体工期目标的课题进行了探讨。
The influence of garage backfill soil of building projects on total construction time was analyzed, it is discussed how to take reasonable management and technical measures to realize the total project duration objective under the conditions of the self-restraining factors of the garage backfilling engineering and environmental factors in- fluences like the winter construction, planting points and dust control.
作者
朱利平
Zhu Liping(China Construction Seventh Engineering Division Co.,Ltd.,Zhengzhou 45000)
出处
《工程建设》
2018年第7期83-87,共5页
Engineering Construction
关键词
车库回填土
工期
因素
措施
garage backfill
construction time
factor
measures