摘要
为了充分利用风能,对风力发电系统最大功率点跟踪(MPPT)进行了研究,基于RT-LAB实时仿真平台搭建了2.5MW直驱式永磁风力发电系统仿真模型,对不同风速条件下,直驱式永磁风力发电系统工作情况进行了实时仿真实验,根据实验结果分析了不同风速下最大功率跟踪的特性,研究结果表明:基于RT-LAB建立的2.5MW永磁直驱风力发电系统实现了最大功率跟踪。
In order to make full use of wind energy,the maximum power point tracking( MPPT) of wind power generation system was studied. Based on RT-LAB real-time simulation platform,a 2. 5 MW direct drive permanent magnet wind power generation system simulation model was established. Under different wind speed conditions,The real time simulation experiment of the working conditions of direct-drive permanent magnet wind power generation system is carried out. The results show that the 2. 5 MW permanent magnet direct drive wind power generation system based on RT-LAB achieves maximum power tracking.
作者
黄明明
HUANG Ming-ming(School of Electrical Engineering,Guangxi University,Nanning 530004,China)
出处
《电气开关》
2018年第4期63-66,共4页
Electric Switchgear
关键词
直驱式永磁同步风力发电机
最大功率点跟踪
实时仿真
direct drive permanent magnet synchronous wind turbine(PMSG)
maximum power point tracking(MPPT)
real time simulation