摘要
为了确保铺龙湾矿4205工作面顺利安全通过受断层影响的探水巷T3,在分析了探水巷T3与工作面层位关系的基础上,制定了安全过探水巷的方案,并辅以必要的安全辅助措施,成功地保障了工作面快速推过该探水巷,为矿井过该类型老巷尤其是探水巷奠定了基础。
In order to ensure that the Longwan mine 4205 working face successfully through the affected by the fault exploration roadway T3,based on the analysis of the exploration of roadway and working face T3 layer relationship, established safe exploration roadway plan, safe and necessary auxiliary measures, to ensure the success of working face quickly pushed through the exploration roadway, laid the foundation for the type of mine roadway especially exploration roadway.
作者
刘谋珍
Liu Mouzhen(Shanxi Pulongwan Coal Industry Co.Ltd. , Datong Shanxi 03710)
出处
《煤矿现代化》
2018年第6期176-177,180,共3页
Coal Mine Modernization
关键词
断层
探水巷
层位关系
方案
辅助措施
fault
exploration roadway
hierarchical relations
scheme
auxiliary measures