摘要
黄岩汇煤矿15111工作面,寺家庄铁路压煤662.8m,开拓巷道掘进滞后。特殊条件下利用铁路压煤区设计措施巷(煤巷),开拓巷道、措施巷两条线平行作业,共设计五个贯通,提前完成采掘接续的综合效益分析。
The 15111 working face of Huangyan Hui coal mine and 662.8 meters of coal pressing coal in Sijiazhuang railway are lagging behind. Under the special conditions, we use the design measures of the railway coal pressure area(roadway), and develop the parallel operation of the two lines of the roadway and the measure lane. We design a comprehensive benefit analysis of five connections and finish the excavation and connection ahead of schedule.
作者
李春刚
Li Chungang(China coal Xiyang Energy Co., Ltd. , Shanxi Jinzhong 04530)
出处
《煤矿现代化》
2018年第6期190-192,共3页
Coal Mine Modernization
关键词
铁路压煤
措施巷
施工管理
贯通
综合效益
railway coal pressing
measures lane
constructionmanagement
penetration
comprehensive benefit