上跨高速铁路连续箱梁顶推施工滑块控制技术研究 被引量:7

Research on Sliding Control Technology for Pushing Continuous Box Girder Crossing Over High-speed Railway
下载PDF
导出
摘要 为了保证连续箱梁顶推法施工过程中的安全,以荆州市蒙华铁路主桥顶推法施工过程为工程背景,通过理论分析与现场试验相结合的技术手段,研究出连续箱梁顶推过程中新型滑道梁同步定位施工滑块技术和施工过程中避免滑块落入营业线技术,主要研究结论如下:(1)从桥梁的结构和控制技术上进行了分析,解决了箱梁爬行和梁体开裂的技术难题;(2)采用滑道系统与钢对钢滑移相结合的技术,精确控制滑块的同步位移;(3)采用滑块掉落处滑道梁开槽措施,保障顶推过程安全施工。 In order to ensure the safety during the construction of continuous box girder with incremental launching method, the technology about simultaneous position of sliding block and remedial measures of preventing sliding blocks into operating lines are studied through the combination of theoretical analysis and field tests based on the main bridge construction of Menghua Railway in Jingzhou, Hubei. The main conclusions are as follows : (1) the difficulties of box girder pushing and beam cracking are solved by the analysis of bridge structure and control technology. (2) The synchronous displacement of sliding block is precisely controlled by combining the slideway system and steel-to-steel slipping technology. (3)The safety is ensured by track beam slotting at places where the sliding blocks drop.
作者 周大勇 Zhou Dayong(China Railway 14^th Bureau Group 2^nd Engineering Co.Ltd.,Tai' an Shandong 271000,China)
出处 《铁道建筑技术》 2018年第7期39-42,共4页 Railway Construction Technology
基金 中铁十四局集团有限公司科技研发计划项目(KJ16-13)
关键词 连续箱梁 顶推法 施工滑块 安全控制 continuous box girder incremental launching method construction slider safety control
  • 相关文献

参考文献9

二级参考文献88

共引文献200

同被引文献54

引证文献7

二级引证文献32

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部