以双模式盾构施工煤矿斜井工程为例,从双模式盾构选型与配置、斜向始发及连续下坡掘进、原位无扩大硐室拆解等关键问题对潜在的施工风险进行了深入分析,并提出了相应对策,可供后续工程施工借鉴和参考。
This article took the coal mine inclined shaft constructed by shield method as an example, conducted an in-depth analysis of the potential construction risks in terms of the selection and configuration of dual-mode shield, diagonal originating and continuous downhill excavation, in-situ non-expanding chamber dismantling and other key issues, and put forward the corresponding countermeasures, which could provide application references for future similar engineering.
作者
李守彪
Li Shoubiao(China Railway Construction Kunlun Investment Group Co.Ltd.,Chengdu Sichuan 610000,China)
出处
《铁道建筑技术》
2018年第7期81-85,共5页
Railway Construction Technology
基金
国家科技支撑计划资助项目(2013BAB10B02)
关键词
煤矿斜井
双模式盾构
复杂地质
施工风险
inclined shaft of coal mine
dual-mode shield
complex geology
construction risk