如何提高立井过空巷时的施工安全技术水平

Discussion on how to improve the construction safety technology level for the vertical shaft crossing the abandoned roadway
下载PDF
导出
摘要 施工矿建工程回风立井期间,在物探后打钻探孔时经常会遇到有空巷,如何安全、高效的保证立井施工顺利穿越空巷显得尤为重要。主要介绍了注浆掘进的施工方法,对其施工要点进行了总结,并阐述了其施工安全注意事项,从而提高立井过空巷时的施工安全技术水平。 During the returning wind vertical shaft of the construction mine construction engineering, it always encounters abandoned roadway in drilling after geophysical prospecting. Therefore, it is rather important for how to safely and efficiently guarantee the vertical shaft construction smoothly crossing the abandoned roadway. The paper mainly introduces the grouting digging construction methods, summnarizes its construction points, illustrates the construction safety matters, so as to improve the construction safety technology level of the vertical shaft crossing the aban- doned roadway.
作者 娄湘峰 Lou Xiangfeng(Railway Transportation Branch Company,Yangquan Coal Industry(Group)Co.,Ltd,Yangquan 045000,China)
出处 《山西建筑》 2018年第23期93-94,共2页 Shanxi Architecture
关键词 立井 空巷 注浆 vertical shaft abandoned roadway grouting
  • 相关文献

参考文献2

二级参考文献2

  • 1董方庭.巷道围岩松动圈支护理论及应用技术[M].北京:煤炭工业出版社,2000.60-88.
  • 2李苏龙.整合矿井采空区内掘进巷道围岩加固支护技术[M].北京:煤炭工业出版社,2012:38-41.

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部