摘要 针对秦山第二核电厂#2机组凝汽器B喉部膨胀节破裂导致的停机停堆事件,对凝汽器喉部膨胀节检修进行跟踪,同时与#3、#4机组金属膨胀节相关情况进行对比,探讨了凝汽器膨胀节检修工作和目前该结构存在的问题,并提出了改进建议,以保证电厂汽轮机的稳定运行。 In view of the halt and reactor shutdown caused by the damage of throat B expansion joint of a condenser,unit2 in the second Qinshan nuclear power plant,the maintenance of the condenser expansion joint is tracked,and a comparison is made between this and the relevant circumstances of metal expansion joints of unit 3 and unit 4.It also discusses the maintenance of condenser expansion joint and the existing problems.At last,suggestions for improvement are put forward to ensure the stable operation of the steam turbine in power plant.
作者 王启峰 邱波 WANG Qifeng;QIU Bo(CNNP Nuclear Power Operations Management Co.,Ltd.,Jiaxing 314300,China)
出处 《电工技术》 2018年第13期123-124,127,共3页 Electric Engineering
关键词 核电厂 凝汽器 橡胶膨胀节 金属膨胀节 裂纹 nuclear power plant condenser rubber expansion joint metal expansion joint crack
  • 相关文献

参考文献3

二级参考文献14

共引文献24

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部