期刊文献+

预制装配式建筑施工中的灌浆套筒连接技术 被引量:6

Joint Technology of Grouting Sleeve for Prefabricated Building Construction
下载PDF
导出
摘要 结合上海临港重装备产业区H36-02地块项目,对预制装配式建筑施工中灌浆套筒连接的技术特点和工艺流程进行了介绍,并从灌浆套筒性能影响因素、施工人员要求、进场检测、灌浆腔密封、灌浆作业、施工扰动等方面详细总结了施工质量控制措施,以期为预制装配式建筑的发展提供借鉴。 Combined with the plot H36-02 project of Shanghai Lingang Heavy Equipment Industrial Zone, the technical characteristics and process flow of the grouting sleeve connection in prefabricated building construction are introduced. In addition, a detailed summary of quality control measures based on several aspects including impact factors of grouting sleeve performance, requirements for construction workers, Incoming testing, sealing over the grouting sleeve, grouting operation, construction perturbation and so on are given in this paper, so as to provide references for the development of prefabricated buildings.
作者 姜泰 JIANG Tai(Shanghai Lingang Innovation Economic Development Service Co.,Ltd.,Shanghai 201403,China)
出处 《建筑施工》 2018年第9期1516-1517,共2页 Building Construction
关键词 预制装配式 施工技术 灌浆套筒 质量控制 prefabricated construction technology grouting sleeve quality control
  • 相关文献

参考文献4

二级参考文献39

  • 103G 329-1.建筑物抗震构造详图[S].,..
  • 2GB50204-2002.混凝土结构工程施工质量验收规范[S].[S].,2002..
  • 3安徽省质量技术监督局.DB34/T810-2008 叠合板式混凝土剪力墙结构技术规程[S].合肥:安徽省质量技术监督局,2008.
  • 4SJG18-2009,预制装配整体式钢筋混凝土结构技术规范[S].
  • 5土木401-1996,混凝土工程设计规范与解说[S].
  • 608sJ 110-2,08SG333,预制混凝士外墙挂板[S].
  • 7JGJ/T 1-1991,装配式大板居住建筑设计与施工规程[S].
  • 8苏JG/T006-2005,预制预应力装配整体式框架(世构体系)技术规程[S].
  • 9AS3600-2001.Concrete Structure[S].
  • 10JASS14,幕墙工程标准[S].

共引文献492

同被引文献34

引证文献6

二级引证文献27

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部