连续大跨度钢桁梁顶推施工监控技术研究 被引量:5

A Study of the Monitoring Techniques for the Incremental Launching Construction of a Continuous Large-Span Steel Truss Beam
下载PDF
导出
摘要 结合黄大铁路黄河特大桥的(120+4×180+120)m连续钢桁梁顶推施工,介绍了钢桁梁顶推过程中的监控技术及措施。利用数值模拟仿真计算,检验钢桁梁各杆件安全性并提出较弱杆件加固措施;综合利用应力应变监控元件及挠度监控措施,监控钢桁梁顶推实际应力应变情况;利用千斤顶精确调整各节点间的相对标高,控制桥梁三维姿态,调整各支点反力,保证钢桁梁的成桥线形。各项措施的综合应用,确保桥梁成桥状态达到最优。 With the incremental launching construction of the (120+4×180+120)m continuous steel truss beams of the Yellow River Mega Bridge of the Huang-Da Railway as the background,the monitoring techniques and measures adopted in the course of launching the steel truss beams are introduced in the paper. The numerical simulation calculation is used to test the security of all the members of the steel truss beam in the paper,with the corresponding measures to strengthen the weaker members presented.Upon the basis of comprehensively using the stress-strain-monitoring components and the deflection-monitoring measures,the real stress and strain of the steel truss beam in the course of being launched are monitored.Jacks are used to adjust the relative elevation among all nodes so as to control the 3-dimensional attitude of the bridge and adjust the counter-force of each fulcrum in order to ensure the bridge-forming linearity of the steel truss beam.As all the above-mentioned measures are comprehensively adopted,the optimization of the bridge-forming state is achieved.
作者 何佳轩 王定举 HE Jiaxuan;WANG Dingju(The Huang-Da Railway Co.Ltd.,Dongying 257091,China)
出处 《国防交通工程与技术》 2018年第5期54-57,66,共5页 Traffic Engineering and Technology for National Defence
关键词 连续钢桁梁 线形控制 三维姿态 continuous steel truss beam linear control 3 dimensional attitude
  • 相关文献

参考文献6

二级参考文献50

共引文献107

同被引文献31

引证文献5

二级引证文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部