摘要
对互感器装置现场校验过程中的特殊性进行分析,阐述了校验开始之前的准备工作和相关工作内容与步骤,探讨了现场校验过程中可能出现的问题,提出了相应的处理方法,为互感器装置现场校验提供参考。
This paper analyzes the par ticularit y of the field check process of the transformer device,points out the relevant work contents and steps of the preparation before the check work and the on-site verification of the transformer,and probes into the possible problems in the field verification process,and puts forward the corresponding treatment methods,hoping to be able to install the transformer for the transformer. Provide some reference for on-site verification.
作者
梁海东
慕晓
梁惠文
李亚琴
赵晓燕
王桢
LIANG Hai-dong,MU Xiao,LIANG Hui-wen,LI Ya-qin,ZHAO Xiao-yan,WANG Zhen(State Grid Shandong Electric Power Company Yantai Power Supply Company, Yantai 264000, Chin)
出处
《通信电源技术》
2018年第6期156-157,共2页
Telecom Power Technology
关键词
互感器
现场校验
绝缘电阻
mutual inductor
field check
insulation resistance