导管架滑移装船过程中驳船/码头滑道许用高差包络线研究 被引量:1

Research on Allowable Deflection Envelope of Barge/Yard Skidway During the Skidded Loadout of Jacket
下载PDF
导出
摘要 滑移装船是目前海洋工程领域常用的深水导管架装船方式。在装船过程中保证驳船滑道与建造码头滑道齐平,避免导管架出现较大变形和剪力,对整个装船过程的安全实施有很重要的意义。基于导管架、驳船和码头滑道强度要求,对某导管架滑移装船过程中每一个施工步骤的驳船与码头滑道的许用最大高差进行了研究,得到了装船过程中的许用高差包络线,用于指导驳船压载方案的制定。研究结果可为同类工程提供参考。 Skidded loadout is the most common loadout method for deepwater jackets.During the skidded loadout of jackets,it is very important to keep the elevation of the barge skidway as close as possible to that of the fabrication yard skidway.Otherwise,large deflection and shear force will be induced in the jacket.Based on the strength requirements of the jacket,barge and yard skidway,the allowable deflection between barge and yard skidway is analyzed for every step of the jacket skidded loadout operation.Finally,the allowable deflection envelope of barge/yard skidway is produced,which will be the guideline for the development of the ballasting scheme of barge loadout.This research will provide reference for similar jacket skidded loadout projects.
作者 黄怀州 刘钊 刘玉玺 HUANG Huai-zhou;LIU Zhao;LIU Yu-xi(Offshore Oil Engineering Co.,Ltd.,Tianjin 300451,China)
出处 《海洋工程装备与技术》 2018年第4期278-282,共5页 Ocean Engineering Equipment and Technology
关键词 导管架 滑移装船 驳船滑道 码头滑道 许用高差包络线 压载 jacket skidded loadout barge skidway yard skidway allowable deflection envelope ballasting
  • 相关文献

参考文献5

二级参考文献13

  • 1梅孝恒,周延东,樊之夏.带有间断不对称式滑靴的大型结构物拖拉滑移装船技术[J].中国海上油气(工程),1997,9(2):1-7. 被引量:20
  • 2API RP 2A - WSD 21st Edition. Recommended Practice for Planning, Designing and Constructing fixed Offshore Platforms - Working Stress Design[M]. 2000.
  • 3American Institute of Steel Construction (AISC). Manual of Steel Construction - Allowable Stress Design[M]. 9th Edition, 1989.
  • 4NOBLE DENTON. Guidelines for load-outs[M].GL,2002.
  • 5DN*v;.lules for Planning and Execution of Marine Operations[S].2000.
  • 6Noble Denton International Ltd. Guidelines for Loadouts (Report No 0013/NDI)[R].2010.
  • 7API RP 2A "Recommended Practice for Planning, Designing, and Constructing Fixed Offshore Platforms", Working Stress Design 21 st Edition (2007).
  • 8American Institute of Steel Construction (AISC).Manual of Steel Construction-Allowable Stress Design. 13th Edition.
  • 9郭庆,高静坤.大型导管架的装船分析[J].中国造船,2008,49(A02):316-320. 被引量:9
  • 10李新超.超大型导管架滑移装船方法研究[J].中国水运(下半月),2013,13(3):33-34. 被引量:11

共引文献26

同被引文献1

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部