海上平台新增主电站带载测试与并网方案

Main Generator Load Test and Paralleling Connection Without Power Shutdown on Offshore Platform
下载PDF
导出
摘要 以渤海垦利油田群为例,设计新增燃气透平发电机组在平台不停产、不断电情况下的调试方案。对传统的负载试验方案进行优化,减少干式电阻箱的使用数量,在实践中取得良好的效果和经济效益。证实方案的可行性,探索大型电站在海上平台并网调试的新思路。 Taken Bohai Kenli oil field group as an example,the commissioning scheme of new gas turbine generating unit under the condition of no power failure and continuous power supply is designed.The traditional load test scheme is optimized,and the number of dry-type resistance boxes is reduced.It achieves good results and economic benefits in practice.The feasibility of the scheme is confirmed,and a new idea of large-scale power station commissioning on offshore platform is explored.
作者 孟凡然 MENG Fanran(Tianjin Branch,CNOOC(China)Co.,Ltd.,Tianjin 300452,China)
出处 《中国海洋平台》 2018年第4期22-26,31,共6页 China offshore Platform
关键词 海洋生产平台 透平发电机组 调试 并网 offshore platform gas turbine generator commissioning paralleling
  • 相关文献

参考文献1

二级参考文献1

  • 1中国船级社.钢制海船入级与建造规范:4.1.7交流发电机[S].北京:人民交通出版社,2009.

共引文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部