以太原市卧虎山2×100 m钢箱梁T构转体桥施工技术为例,分析了T构转体的施工流程,总结了T构转体施工前的准备工作以及正式转体过程中的施工要点和控制措施,该研究对钢箱梁T构转体施工具有一定的参考意义。
Taking the construction technology of 2 × 100 m steel box beam T constitutive swivel bridge in Wohu Mountain of Taiyuan City,the construction process of T constitutive swivel bridge is analyzed. The preparation work before construction,construction points and control measures in the process of swivel are summarized. The research has a certain reference meaning for realization of the construction technology of constitutive swivel bridge.
作者
杜红燕
Du Hongyan(Taiyuan Municipal Public Engineering Quality Supervision Station, Taiyuan 030012, China)
出处
《山西建筑》
2018年第26期161-162,共2页
Shanxi Architecture
关键词
钢箱梁
T构转体
施工技术
steel box beam
T constitutive swivel
construction technology