北京新机场航站楼核心区结构平面超大,且工期紧张,在混凝土结构阶段施工时,应用多项施工组织技术对施工平面部署进行统筹安排,确保在预定工期内完成了混凝土结构施工。
The core area structure of Beijing Daxing International Airport covers a super-large plan area and has a tight construction schedule. Therefore, various construction organization techniques were adopted during concrete structure construction, to effectively arrange the construction plan layout ad to guarantee completion of concrete structure construction within the planed schedule.
作者
李建华
谢文东
程欣荣
刘汉朝
刘铸玮
LI Jian-hua;XIE Wen-dong;CHENG Xin-rong;LIU Han-chao;LIU Zhu-wei(Beijing Urban Construction Group Co.,Ltd.,100088,Beijing,China)
出处
《建筑技术》
2018年第9期925-928,共4页
Architecture Technology
基金
北京市科技计划课题(Z161100005116009)
关键词
北京新机场
超大平面
混凝土结构
施工组织
Beijing Daxing International Airport
super-large plan area
concrete structure
constructionorganization