摘要 介绍了智能变电站二次系统联调的基本内容和主要流程,分析了二次联调对于智能变电站设备互操作性和同步性验证的重要作用,指出二次联调是智能变电站建设过程中不可或缺的一环,并以220kV智能变电站二次系统联调过程为例,探讨了联调各部分的具体方案,总结了联调所需设备配置和注意事项,对联调过程中的部分关键问题提出了建议及解决方案. This paper firstly introduces the main contents and process of smart substation integrated testing, and then it analyses the important role that integrated testing plays in the check of the correlation among relay system. A viable project is proposed for the test when discussing the process of 220kV smart substation integrated testing. Besides, the paper points out several matters needing attention which are significant to the test of relay systems.
作者 丁鸿 杨勇 韩磊 童大中 DING Hong;YANG Yong;HAN Lei;TONG Dazhong(Huzhou Power Supply Company,State Grid Zhejiang Electric Power Corporation,Huzhou 313000,China)
出处 《湖州师范学院学报》 2018年第8期42-45,共4页 Journal of Huzhou University
关键词 智能变电站 二次系统 联合调试 方案 smart substation relay system integrated testing project
  • 相关文献

参考文献3

二级参考文献20

共引文献34

同被引文献15

引证文献2

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部