摘要
对RBC切换原则进行说明,结合杭黄客专黄山北枢纽实际站场对RBC切换方案进行分析,针对实际线路不满足RBC通信切换的条件,提出通过CTCS-3转CTCS-2和联锁代传信号授权延伸RBC数据覆盖范围,以解决场间列车跨线运行的问题。
This paper describes the principle of RBC handover and analyzes the RBC handover scheme based on the real yard situation of Huangshanbei station of Hang-Huang dedicated passenger line(DPL). For the problem that an operational line cannot satisfy the communication condition of RBC handover, it puts forward a solution to add level transition from CTCS level 3 to level 2 and extend the RBC controlling data scope through sending SA by interlocking.
作者
纪明慧
Ji Minghui(Beijing National Railway Research & Design Institute of Signal & Communication Group Co.,Ltd.,Beijing 100070,China;Beijing Engineering Technology Research Center of Operation Control Systems for High Speed Railways,Beijing 100070,China)
出处
《铁路通信信号工程技术》
2018年第9期6-9,共4页
Railway Signalling & Communication Engineering