摘要
水电站枢纽系统结构复杂,开挖过程中超挖现象普遍,因此,在猴子岩尾水闸室设计中,采用BIM正向设计,进行三维出图,直观表达了塔体结构及配筋布置,有效提高了工作效率;同时结合GIS系统,可根据现场开挖情况动态更新设计方案,优化塔体两侧回填混凝土工程量。
The structure system of hydropower station is very complicated. Overbreaking often occurs during excavation. Therefore,BIM is adopted in the design of tailrace gate chamber and 3D drawing is given. The tower structure and steel bar arrangement is presented clearly and work efficiency is significantly improved; In addition,combined GIS system,the design can be dynamically updated according to the site excavation conditions. The amount of backfill concrete is greatly optimized in two sides of tower structures.
出处
《四川水力发电》
2018年第5期120-122,共3页
Sichuan Hydropower
关键词
BIM
模型建立
三维出图
优化及调整
BIM
model development
3D drawings
optimization and adjustment