在对峨眉城市中心综合体建设项目山上住宅工程(二期)C区(鱼塘回填区)填土及填方边坡岩土工程勘察报告分析基础上,总结采用的工作方法及取得成果,为后期类似勘察工作方法提供参考依据。
Based on the analysis of the survey report on the geotechuical engineering survey office filling soil and the filling slope in district C (fishpond backfill area) of the mountain residential project (phase Ⅱ ) of the central complex construction project in Emeishan city, the working methods and achievcrncnts adopted are analyzed to provide reference for similar investigation methods in the later period.
作者
张青云
邓春艳
ZHANG Qing-yun;DENG Chun-yan(Sichuan Geology and Mineral Bureau 403 Geological Team,Emeishan 614200,China)
出处
《工程建设与设计》
2018年第19期64-66,69,共4页
Construction & Design for Engineering
关键词
工程地质条件
现场试验
工作方法
取得参数
后期应用
engineering geological conditions
field test
working methods
get parameters
late application