摘要
针对变电站中置开关柜的转运、就位等工艺受到开关室、电缆沟、施工地面等因素限制,无法采用大型机械进行作业,探讨一种适用于变电站室内开关柜转运、对接就位的方法,提高中置开关柜室内施工作业的质量和效率。
To the restrictions problem of switching rooms,cable trenches,construction ground and other factors,large machinery cannot be used for the transfer and location of the switchgear in the substation.A method suitable for transfer and docking of switchboards in substations was discussed.The quality and efficiency of the construction of the middle switchgear cabinet were improved.
作者
夏宗杰
倪汇川
李传江
XIA Zongjie;NI Huichuan;LI Chuanjiang(Tongling Power Supply Company,State Grid Anhui Electric Power Company,Tongling 244000,China)
出处
《电工技术》
2018年第17期118-119,124,共3页
Electric Engineering
关键词
变电站
开关柜
转运
就位
小车
substation
switch cabinet
transfer
location
vehicle