摘要
针对#3机组C相主变现场局部放电试验不合格问题,通过现场检查和吊罩解体检查找到故障点,并对造成局放试验不合格原因进行分析,给出相应结论及建议。
The problem of unqualified partial discharge test of unit 3 Cphase main transformer was studied.Through onsite detection and hanging cover inspection,the failure was found.The reasons for the unqualified partial discharge test were analyzed,and corresponding conclusions and suggestions were given.
作者
薛杰
佟小明
章勇
XUE Jie;TONG Xiaoming;ZHANG Yong(Jiangsu Nuclear Power Co.,Ltd.,China Nuclear Power,Lianyungang 222042,China)
出处
《电工技术》
2018年第17期147-148,151,共3页
Electric Engineering
关键词
核电站
主变
局部放电试验
主绝缘
受潮
nuclear power plant
main transformer
partial discharge test
main insulation
dampness