摘要
根据喀热苏水利枢纽工程水文、气象和地形地质条件,结合水工建筑物的布置情况和施工要求,提出施工导流采用分期导流方式,简述了3个时段的导流时间、渡汛标准、导流程序以及施工导截流建筑物设计要点。
Stage diversion scheme was determined for Karesu Hydraulic Project according to the hydrological, meteo- rological, topographical and geological conditions, and combined with the layout and construction requirements of hydraulic structures. A brief introduction was made on the three diversion periods, flood standard, diversion process and key points of design of construction diversion and river closure structures.
作者
杨造仁
YANG Zao-ren(Xinjiang Water Conservancy and Hydropower Survey and Design Institute,Urumqi 830000,China)
出处
《广西水利水电》
2018年第5期27-29,32,共4页
Guangxi Water Resources & Hydropower Engineering
关键词
施工导流
设计
分期导流
方式
Construction diversion
design
stage diversion
pattern