介绍了广西北海市合浦县总江水闸除险加固工程的基本情况。对"膜袋充砂围堰+钢板桩防渗心墙"和"土石围堰+高压旋喷灌浆防渗心墙"全断面围堰施工导流方案进行了综合比较。结合总江水闸挡河闸坝施工导流实践,论述了膜袋充砂围堰+钢板桩防渗心墙全断面围堰施工导流的施工方法。
An introduction was made on the general information of Zongjiang Water Gate Reinforcement Project at Hepu County, Beihai City of Guangxi. Two full-section cofferdam diversion alternatives were compared. The determined scheme incorporates cofferdam constructed by membrane bag filled with sand and steel piling impervious core. Another alternative incorporates earth-rock cofferdam and high pressure jet grouting impervious core. Combined with the construction diversion practice at Zongjiang water gate, the author discussed the construction methods of the determined scheme.
作者
唐爱学
TANG Ai-xue(Haihe Water Conservancy Construction Co.,Ltd.,Guangxi Construction Engineering Group,Nanning 530200,China)
出处
《广西水利水电》
2018年第5期39-44,共6页
Guangxi Water Resources & Hydropower Engineering
关键词
膜袋充砂围堰
U型钢板桩
U型钢板桩防渗心墙
全断面围堰导流
施工技术
总江水闸
Cofferdam constructed by membrane bag filled with sand
U-pattern steel piling
U-pattern steel piling impervious core
full-section cofferdam diversion
construction technique
Zongjiang water gate