摘要
CL体系可以保证建筑热工性能的稳定,在其施工时,需要混凝土垫块的制作安装以便于后续工序顺利进行。制作混凝土垫块,可以保证钢筋保护层的厚度,又可以与结构更好的结合,保障CL体系的施工质量。
The CL system can ensure the stability of the thermal performance of the building. In its construction, it is necessary to make and install the concrete cushion block so as to facilitate the subsequent process to proceed smoothly. Making concrete padding blocks can guarantee the thickness of the steel bar protection layer, and can combine with the structure better, so as to guarantee the construction quality of the CL system.
作者
张大伟
ZHANG Da-wei(Department of Construction Engineering,Chengde Petroleum College,Chengde 067000,Hebei,China)
出处
《承德石油高等专科学校学报》
CAS
2018年第5期57-58,70,共3页
Journal of Chengde Petroleum College
关键词
CL体系
垫块
模具
CL system
padding block
mold