通过优化42205综采工作面风桥设计,将422盘区42205工作面的3条回采巷道变为422盘区隧道北区42201-42204工作面的开拓大巷,既减少了巷道施工工程量,又能满足各工作面回采期间的运输和通风需要,取得了较好的经济效益。
By optimizing the design of air crossing in No. 42205 fully mechanized mining face, three mining roadways of No. 42205 working face in No. 422 panel are changed into the development roadways of No. 42201- No. 42204 working faces in north of No.422 panel,which not only reduces the amount of roadway construction, but also meets the transportation and ventilation requirements of each working face during the mining period, and achieves better economic benefits.
作者
董卫峰
DONG Wei-feng(Shaanxi Huisen Coal Industry Development Co.,Ltd.,Xi'an 710045,China)
出处
《陕西煤炭》
2018年第6期36-39,共4页
Shaanxi Coal
关键词
综采工作面
通风系统
风桥
优化设计
fully mechanized mining face
ventilation system
air crossing
optimization design