摘要
莱索托麦特隆大坝及原水泵站工程是在FIDIC合同条件、多国际基金和世界银行监管下运作的纯国际商业投资项目。承包人利用FIDIC合同条件,初期实现142天工期索赔,降低了履约风险,促使项目扭亏为盈。本文介绍了承包人利用业主提供条件和开工延期导致水文气象条件变化而进行工期索赔的成功经验,从合同条件和工程技术两方面进行分析,提出了六个方面的索赔因素和注意事项,可供同类工程借鉴。
Lesotho Metolong Dam and Raw Water Pump Station Project belongs to pure international commercial investment project operated under FIDIC contract conditions, multi-international funds and world bank supervision. The contractor uses FIDIC contract conditions for realizing claims for 142-day construction period at the initial stage, thereby reducing the risk of contract performance and promoting the project to turn the loss into profit. Successful experience of the contractor in utilizing conditions provided by the owner and claiming the construction period due to changes in hydrometeorological conditions caused by commencement delay are introduced in the paper. Contract conditions and engineering technology are analyzed, claim factors and precautions in six aspects are proposed, thereby providing reference for similar projects.
作者
罗继忠
刘细军
周政国
LUO Jizhong;LIU Xijun;ZHOU Zhengguo(Sinohydro Bureau 8 Co.,Ltd.,Changsha 410004,China)
出处
《水利建设与管理》
2018年第11期53-57,共5页
Water Conservancy Construction and Management
关键词
菲迪克合同条件
工期索赔
水文气象
关键路径
业主提供条件
FIDIC contract conditions
construction period claim
hydrometeorology
critical path
conditions provided by the owner