高阳矿31108工作面疏放上组煤积水实践 被引量:1

Practice on Dredge Seeper in 31108 Working Face of Gaoyang Colliery
下载PDF
导出
摘要 针对高阳煤矿31108工作面上组煤采空区积水问题,根据水文地质条件,采用理论计算及现场实践的方法,疏放了上组煤采空积水。计算得上组煤积水量为6240.8 m3,并在31108工作面布置6个钻孔进行采空区积水的疏放,截至2017年7月18日疏放采空积水约7469 m3,疏放上组煤积水效果良好。同时,进行了6次水质化验,据化验结果分析,工作面掘进过程中取得的淋水水样均为太灰水,放水孔水样为老空水。 Based on the actual hydrogeological conditions of coal mines on 31108 working face of Gaoyang Colliery, theoretical calculations and field practice methods have been used to discharge the upper group of coal mined water. Conclusions have been drawn that the amount of coal in the upper group is 6240.8 m^3, and 6 holes are arranged in the 31108 working face for the drainage of water in the goal. As of July 18, 2017, the water in the goal is about 7469 m^3, which proves good effect of draining coal water in the upper group. At the same time, six water quality tests have been conducted. According to the analysis of laboratory resuhs, the water samples obtained during the excavation of the working face are all gray water, and the water sample in the water discharge hole is goal water.
作者 牛冬冬 Niu Dongdong(Dept.of Geology & Survey,Fenxi Mining Group,Jiexiu Shanxi 03200)
出处 《江西煤炭科技》 2018年第4期146-147,150,共3页 Jiangxi Coal Science & Technology
关键词 采空区积水 疏放积水 放水钻孔 goal seeper dredge seeper drainage borehole
  • 相关文献

参考文献5

二级参考文献17

共引文献55

同被引文献6

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部