摘要 论文通过对某核电厂大修工作许可证的流程及存在的问题进行分析,提出了通过流程优化、资源整合等方式,在确保核电站工作安全的前提下,降低工作许可证出票数量、减轻人员的工作负荷、降低人因失误概率,实现工作许可证流程的精益管理和成本有效控制。 The paper explores the procedure of the overhaul work permit of a nuclear power plant and analyzes the existing problems,and puts forward the way of process optimization and resource integration, which can reduce the number of work permits issued, the workload of personnel, the human error probability under the premise of ensuring the work safety of the nuclear power plant. It also can realize the lean management of the work permit process and the effective control of costs.
作者 刘丹 唐相恒 LIU Dan;TANG Xiang-heng(China General Nuclear Operations and Management Co.Ltd.,Shenzhen 518124,China)
出处 《中小企业管理与科技》 2018年第33期29-30,共2页 Management & Technology of SME
关键词 核电厂 工作许可证 精益管理 成本控制 nuclear power plant working permit lean management cost control
  • 相关文献

同被引文献2

引证文献2

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部