摘要
以上海崇明岛某吹填工程为案例,详细阐述了沉降值估算法在吹填工程中的具体应用,介绍了沉降值的计算方法,旨在通过实证分析,为吹填工程施工过程中的沉降值估算提供一定的理论参考,为提升吹填工程设计水平,优化经济效益,促进资源合理利用发挥积极作用。
Taking a dredger filling project in Chongming island of Shanghai as an example, this paper expounds the application of settlement value estimation method in dredger filling project, and introduces the calculation method of settlement value. The purpose of this paper is to provide a theoretical reference for the settlement value estimation during the construction of dredger filling project, and improve the design level of dredger filling project, optimize economic benefits and promote the rational use of resources.
作者
王启贵
姜珍妮
WANG Qi-gui;JIANG Zhen-ni(Zhejiang Huadong Engineering Safety Technology Co.Ltd.,Hangzhou 311122,China;Wenzhou Oujiangkou Municipal Garden Co.Ltd.,Wenzhou 325000,China)
出处
《工程建设与设计》
2018年第22期123-124,共2页
Construction & Design for Engineering
关键词
吹填工程
沉降值
估算法
dredger filling engineering
settlement value
estimation method