摘要
详细介绍了2×660MW空冷机组工程汽动给水泵小汽轮机钢结构间冷塔安装采用的分层分段吊装方法,从而加快了施工进度,克服了寒冷气候的影响,提高了劳动效率,有效保证了安全施工和工程质量。
This paper introduces in detail the layered and segmented hoisting method adopted in the installation of the steel structure intercooling tower of the steam-driven feed-water pump small steam turbine for the 2 ×660 MW air-cooled unit project, so as to speed up the construction progress, overcome the impact of cold climate, improve the working efficiency, and effectively ensure the safety construction and engineering quality.
作者
那仁
Naren(Huadian Inner Mongolia Energy Co.Ltd.,Hohhot 010020,China)
出处
《工程建设与设计》
2018年第22期168-169,共2页
Construction & Design for Engineering
关键词
空冷机组
钢结构
间冷塔
单元桁架
吊装
air-cooled unit
steel structure
indirect cooling tower
unit truss
hoisting