摘要
火电厂水处理系统采用水岛的建设模式,在更好实现水梯级使用的同时能节省较多的占地面积和设备投资。对于部分以海水淡化系统产水作为全厂工业用水的沿海火电厂来讲,采用水岛的建设模式意义更大。为此,以某沿海火电厂为例,对该类型火电厂水处理系统采用水岛方式设计的思路加以介绍,在占地面积和经济效益方面与分散布置方式进行对比分析,并给出水岛系统设计的注意要点。分析表明,沿海火电厂水岛集中布置比常规分散布置节约20%的占地面积,且可节省大量的公用设备/设施,在提高水务监管水平的同时,可做到减员增效,经济和环保效益显著。
Thermal power plant water treatment system using the water island construction mode in the water is capable of takingbetter advantage of the cascading water usage while saving more occupied area and equipment investment. For some coastal thermalpower plants that rely on seawater desalination as the industrial water for the whole plant, it is of greater significance to apply theconstruction mode of the water island. Take a coastal thermal power plant as an example, this paper introduces the idea of waterisland system design for this type of thermal power plant water treatment system, analyzes the layout and decentralized arrangementin terms of area and economic benefits, then points out the items that more attention needs to be given in the design of water islandsystem. The analysis shows that the centralized deployment of water islands in coastal thermal power plants occupies 20% of thefloor area less than conventional decentralized arrangements, and it can also save the investment on a large amount of publicfacilities. Therefore the target to downsize staff and improve economic efficiency is reached while the level of water regulation isenhanced with significant economic and environmental benefits.
作者
叶治安
张江涛
孙军峰
慕时荣
YE Zhian;ZHANG Jiangtao;SUN Junfeng;MU Shirong(Xi'an Thermal Power Research Institute Co.,Ltd.,Xi'an 710032,China)
出处
《中国电力》
CSCD
北大核心
2018年第12期180-184,共5页
Electric Power
关键词
火电厂
水处理设计
水岛
海水淡化
分散布置
集中控制
thermal power plant
water treatment design
water island
seawater desalination
decentralized arrangement
centralized control