本文从城市道路路面与检查井顺接的周围是道路的薄弱环节、施工中存在许多难处及给道路竣工后留下许多隐患的现实问题出发 ,并根据自己多年的研究与实际施工经验总结 ,找出检查井与路面顺接不平顺的主要原因 ,提出了解决这一问题的具体措施和施工要求。
The surroundings for direct-connection of urban road surface and inspection pit is a weaken linkage in road construction,and some hidden troubles always remain after completing road construction.Based on study and experience in practical costruction,the author found out the major cause of uneven direct_connection of inspection pit and road surface and put forward the specific measures and requirements for solving this problem.
出处
《森林工程》
北大核心
2002年第5期48-49,共2页
Forest Engineering
关键词
城市道路
路面
检查井
顺接
Urban road
Inspection well
Linkage
Cause